Calculate the issue done ratio from estimated and spent time

Admin Redmine さんがほぼ4年前に追加. ほぼ4年前に更新.

ステータス:
New
優先度:
通常
担当者:
-
カテゴリ:
Issues_2
対象バージョン:
-
開始日:
2011/02/04
期日:
進捗率:

0%

予定工数:
category_id:
2
version_id:
0
issue_org_id:
7545
author_id:
23360
assigned_to_id:
0
comments:
9
status_id:
1
tracker_id:
2
plus1:
5
affected_version:
closed_on:
affected_version_id:
ステータス-->[New]

説明

It is possible to add an option to calculate automatically the done ratio from the relationship between the estimated hours and the real hours? (If we turn the percentage would be greater than 100)

Thanks and congratulations for your work


journals

Typically estimation does not match reality. Someone can estimate a task to take 5hours and is done within 15minutes. Other times after 10hours it still isn't half way complete.

If this were a feature, I would expect to have it turned off on my Redmine instances.

Kind regards

Adam Żochowski
--------------------------------------------------------------------------------
We have the same request in #11999. See our description for the reason why this makes sense anyway. I totally understand Adams' argument. Although in some projects it totally makes sense to have the total issue done ration being calculated based on the spent time value. If *Spent Time* is greater than *Estimated Time* and the option to calculate the done ratio based upon these 2 values is turned on, the done ratio for a task should simply be set to 100%.

Perhaps, when using the option to calculate the done ratio based upon Estimated Time/Spent Time is enabled, the field *Estimated Time* should be renamed to *Time Required* or *Lead Time*. Then it again makes sense.

This is useful for projects where the customer pays for a certain amount of hours (in advance) and has the ability to check the status on the issue he payed for. Thus if *Spent Time* exceeeds *Estimated Time* the bar in the issue overview should become red or something to visualize that an issue is over the "limit".
--------------------------------------------------------------------------------
+1
--------------------------------------------------------------------------------
+1

We can add another field with the estimated remaining time and use it to calculate a more realistic done ratio. Something like this:

1) Starting:
Estimated Time: 8 h
Spent Time: 0 h
Remaining Time: 8 h
% done: 0 %

2) Halfway:
Estimated Time: 8 h
Spent Time: 4 h
Remaining Time: 4 h
% done: 50 %

3) Some delay:
Estimated Time: 8 h
Spent Time: 8 h
Remaining Time: 4 h
% done: 50 %
And since Spent Time + Remaining Time > Estimated Time, we have a delay, and then we should get the red bar to signal it. :D

--------------------------------------------------------------------------------
+1 for a new optional fieled with configurable algorithms from selection below
--------------------------------------------------------------------------------
+1
--------------------------------------------------------------------------------
+1
--------------------------------------------------------------------------------

--------------------------------------------------------------------------------

--------------------------------------------------------------------------------


related_issues

relates,New,12347,"Calculate the issue done ratio" per project configuration
relates,New,11999,Calculating issue done ratio based on "Estimated Time" and "Spent Time" - selectable by project (not globally)

Admin Redmine さんがほぼ4年前に更新

  • カテゴリIssues_2 にセット

他の形式にエクスポート: Atom PDF

いいね!0
いいね!0