未完了Overall completion percent on the project
ステータス:
New
優先度:
通常
担当者:
-
カテゴリ:
Gantt_34
対象バージョン:
-
開始日:
2011/02/05
期日:
進捗率:
0%
予定工数:
Redmineorg_URL:
category_id:
34
version_id:
0
issue_org_id:
7550
author_id:
27316
assigned_to_id:
0
comments:
2
status_id:
1
tracker_id:
2
plus1:
2
affected_version:
closed_on:
affected_version_id:
説明
It would be nice (and useful) that the project bar in the Gantt chart to be similar with the bar of the issues having sub-issues. This way we will know the overall project completion percent, and it will also be a visual representation of it (green and red filling colors).