Vote #69451
完了Gantt- Issues does not show up in green when start and end date are the same
0%
説明
When you have an issue , maybe 4 hours estimated, you pick start and end date for 2011-03-01.
If you close the Ticket it will not show up in green in the gantt chart. When you switch the due date to 2011-03-02 it shows up in green.
maybe you gonna fix this
journals
Confirmed, although it's not status or estimated time related.
If Due date and Start date are equals and issue is 100% Done then issue line keeps being displayed in grey instead of green.
--------------------------------------------------------------------------------
Here's a patch.
--------------------------------------------------------------------------------
--------------------------------------------------------------------------------
Sorry, missed something.
--------------------------------------------------------------------------------
Committed with tests in r5236. I've also fixed a few existing tests that were failing because of the fixed calculation.
--------------------------------------------------------------------------------
--------------------------------------------------------------------------------
related_issues
relates,Closed,8233,100% done 1-day tasks not green on gantt chart