Gantt- Issues does not show up in green when start and end date are the same

Admin Redmine さんが3年以上前に追加. 3年以上前に更新.

ステータス:
Closed
優先度:
通常
担当者:
-
カテゴリ:
Gantt_34
対象バージョン:
開始日:
2022/05/09
期日:
進捗率:

0%

予定工数:
category_id:
34
version_id:
34
issue_org_id:
7838
author_id:
30034
assigned_to_id:
0
comments:
6
status_id:
5
tracker_id:
1
plus1:
0
affected_version:
closed_on:
affected_version_id:
30
ステータス-->[Closed]

説明

When you have an issue , maybe 4 hours estimated, you pick start and end date for 2011-03-01.
If you close the Ticket it will not show up in green in the gantt chart. When you switch the due date to 2011-03-02 it shows up in green.

maybe you gonna fix this


journals

Confirmed, although it's not status or estimated time related.

If Due date and Start date are equals and issue is 100% Done then issue line keeps being displayed in grey instead of green.

--------------------------------------------------------------------------------
Here's a patch.
--------------------------------------------------------------------------------

--------------------------------------------------------------------------------
Sorry, missed something.
--------------------------------------------------------------------------------
Committed with tests in r5236. I've also fixed a few existing tests that were failing because of the fixed calculation.
--------------------------------------------------------------------------------

--------------------------------------------------------------------------------


related_issues

relates,Closed,8233,100% done 1-day tasks not green on gantt chart

Admin Redmine さんが3年以上前に更新