Now, only dependecies "precedes" and "follows" exists to order 2 issues time schedule.
I suggest to add more dependencies according project management:
- FS: end A - start B
- SS: start A - start B
- FF: end A - end B
- SF: start A - end B See eg. http://en.wikipedia.org/wiki/Dependency_(project_management) for a detailed description.
It would allow reschedule of start and due dates of issues base on the dependencies and durations.
Sorry if I submitted a duplicated issue. It is very hard to search in those 2.000+ feature requests.