hello,
We are using redmine to manage our change management processes.
The functional user open end close the issue, other status are dealt by IT team. My problem is that i don’t want to give the functional user the ability to view the history or details of the issue ( what IT team are doing).
My questions are ?
- Can i hide issue details based on user role or permission ?
- Can i disable clickable links to on the issues list view based on role ? If not, what can i do ?
Thanks
journals
Use private comments? #1554?
--------------------------------------------------------------------------------
I have a similar problem and private comments not resolve it.
Status change and reassignment are visible for functional users, but i want to hide it.
Functional user must have ability to see changes of task, only when it assigned to him in this change.
Thanks.
--------------------------------------------------------------------------------
+1, private comments doesn't resolve problem.
--------------------------------------------------------------------------------
--------------------------------------------------------------------------------
--------------------------------------------------------------------------------
+1
--------------------------------------------------------------------------------
--------------------------------------------------------------------------------
--------------------------------------------------------------------------------
Look forward to this feature!
--------------------------------------------------------------------------------
+1
--------------------------------------------------------------------------------
+1
--------------------------------------------------------------------------------
--------------------------------------------------------------------------------
--------------------------------------------------------------------------------
+1
It would be very useful
--------------------------------------------------------------------------------
possible workaround: create subtasks with tracker that is only visible for IT-team (see #285), that way IT-team-history is not visible for other users
--------------------------------------------------------------------------------
Wim DePreter wrote:
> possible workaround: create subtasks with tracker that is only visible for IT-team (see #285), that way IT-team-history is not visible for other users
Thanks for the information !
It works, I will see with our project manager if this workaround can solve this problem for now.
Problems seen with this workaround:
- it's a bit tricky as the status of the parent do not change when the children is updated (only % is updated)
- I got one tracker not visible (the IT one) for 9 trackers visibles by customers (I don't want to duplicate every tracker and get 18 trackers, it will be automatically refused by my hierarchy)
--------------------------------------------------------------------------------
Arnaud Pissot wrote:
> Problems seen with this workaround:
> - it's a bit tricky as the status of the parent do not change when the children is updated (only % is updated)
> - I got one tracker not visible (the IT one) for 9 trackers visibles by customers (I don't want to duplicate every tracker and get 18 trackers, it will be automatically refused by my hierarchy)
It was just a suggestion. We faced the same problem in version 3.0 (#285 wasn't resolved), and created a separate IT-project, used "blocked by" relation instead of subtasks, but that is more complex (extra relation has to be added). We didn't duplicate trackers, because visibility was controlled on project-base.
For status-synchronisation, we have a batch-job (than runs every X minutes) that synchronises states via rest-API.
--------------------------------------------------------------------------------
Wim DePreter wrote:
> Arnaud Pissot wrote:
> > Problems seen with this workaround:
> > - it's a bit tricky as the status of the parent do not change when the children is updated (only % is updated)
> > - I got one tracker not visible (the IT one) for 9 trackers visibles by customers (I don't want to duplicate every tracker and get 18 trackers, it will be automatically refused by my hierarchy)
>
> It was just a suggestion. We faced the same problem in version 3.0 (#285 wasn't resolved), and created a separate IT-project, used "blocked by" relation instead of subtasks, but that is more complex (extra relation has to be added). We didn't duplicate trackers, because visibility was controlled on project-base.
> For status-synchronisation, we have a batch-job (than runs every X minutes) that synchronises states via rest-API.
Yeah I'm really thankful for your solution,
we already have the "Custom workflows" plugin which can allow me to replicate the status of the issue to its parent but I prefer to not use plugins and tricks everywhere to get our Redmine working smooth as possible and avoid bugs :)
--------------------------------------------------------------------------------
+1
--------------------------------------------------------------------------------
related_issues
relates,New,9432,Default value for the private issue flag
duplicates,Closed,24806,Possibility to hide Issue History from a role