Bulk update Start/End Date with different dates for each issue

Admin Redmine さんが約2年前に追加. 約2年前に更新.

ステータス:
Reopend
優先度:
通常
担当者:
-
カテゴリ:
Issues planning_40
対象バージョン:
-
開始日:
2022/05/09
期日:
進捗率:

0%

予定工数:
category_id:
40
version_id:
0
issue_org_id:
15578
author_id:
88426
assigned_to_id:
0
comments:
4
status_id:
8
tracker_id:
2
plus1:
0
affected_version:
closed_on:
affected_version_id:
ステータス-->[Reopend]

説明

At the planning stage of a project normally we make a list of activity then we change the date

It is cumbersome to have to edit the date of for 10 20 or 100 issues.

we could add it to the contextual menu, or simply edit it directly in the table "spreadsheet style"


journals

This is already possible: Select multiple issues, then right-click and select "edit". Change the Start/End Date and that's it. :-)
--------------------------------------------------------------------------------
Sorry to reopen it

If you have 100 issues then they will all have the same dates ...
--------------------------------------------------------------------------------
David Tremblay wrote:
> If you have 100 issues then they will all have the same dates ...
How would that be different if you'd have a context menu?
You asked for bulk updates and I indicate that they are already possible...

If you're seeing this from a project planning POV, then I guess what you'd like to see is more a spreadsheet-like view of all issues in a project, and then edit the dates of the issues to create a order in which the issues have to be executed.

In this case, I recommend uding parent-child relationships, which define an order of execution...
--------------------------------------------------------------------------------

--------------------------------------------------------------------------------