Vote #81480

未完了

Copy Project Tracker and Tasks and relations

Admin Redmine さんがほぼ2年前に追加.

ステータス:
New
優先度:
通常
担当者:
-
カテゴリ:
-
対象バージョン:
-
開始日:
2022/05/09
期日:
進捗率:

0%

予定工数:
category_id:
0
version_id:
0
issue_org_id:
35382
author_id:
523420
assigned_to_id:
0
comments:
1
status_id:
1
tracker_id:
1
plus1:
1
affected_version:
closed_on:
affected_version_id:
165
ステータス-->[New]

説明

In order to manage our Implementation Project better, I created a Project X. In order to better organize our task I also created a tracker for Project.

The trackers I have are:

  • Project
  • Programming Request
  • Support
  • Bug
  • Training

The hierarchy of the project is as follow :

  • Project X ** Project (Tracker) = Project Implementation *** Programming request 1 - Precedes (Support 2) *** Support 2 Precedes (Support 3) *** Support 3

When I make a copy of the Project Implementation, the subtasks Programming request 1, Support 2, Support 3 do copy however the Precedes values does not copy over.

Anyone else has this issue?

Ideally what I would love to do is copy the Project Implementation as a template and push the dates based on the Project Implementation for other projects moving forward


journals

+1 Confirmed
--------------------------------------------------------------------------------